export@ezsteelpipe.com
+86 731 8870 6116
Welding is the make-or-break step for any copper-nickel piping system built to EEMUA 144 and EEMUA 234. The alloy's high thermal conductivity, sensitivity to heat input, and tendency to absorb gases mean that an average steel procedure will not work. This guide walks through the welding procedures that are actually recommended for EEMUA 144 234 Cuni pipe on offshore platforms, in marine & shipbuilding systems, and in seawater cooling loops, and shows how to match each procedure to the pipe you have on site.
The recommendations below are written for project engineers, welding supervisors, and QA inspectors who need a practical procedure they can apply to a real WPS (Welding Procedure Specification) and a real PQR (Procedure Qualification Record). All product and material references are consistent with EZ Steel Industrial's Cuni pipe range.
EEMUA 144 covers 90/10 copper-nickel (UNS C70600, CW 352H) tubes and fittings for offshore use, while EEMUA 234 covers 70/30 copper-nickel (UNS C71500, CW 354H) tubes for the same duty. Both standards call out the same root cause of in-service failures: the welding procedure, not the pipe itself.
Three properties drive the procedure:
A good procedure balances those three risks. The sections below give the recipe.
A EEMUA 144/234 procedure always starts with a documented preparation step, not with striking the arc. The items below should appear in the WPS as mandatory pre-weld checks.
If any of the above cannot be met, stop and raise a deviation report. A clean, well-aligned joint is the single biggest predictor of an in-service weld that passes hydrostatic test.
EEMUA 144/234 do not mandate a single process, but they do restrict the choice. The four processes below are the ones you will see in qualified WPSs on offshore and shipyard projects.
TIG is the recommended process for root passes, all positions, and pipe wall thickness up to about 4 mm. The non-consumable tungsten electrode gives a stable arc, the operator controls heat input by foot pedal, and the gas coverage protects the weld pool from atmospheric contamination.
Hold a short arc (1.5-3 mm). Long arcs draw in atmosphere and cause porosity. Use current ramping at start and end to fill the crater.
MIG is recommended for fill and cap passes on pipe 4 mm and thicker, and for long production runs where deposition rate matters. Use a push-pull torch to feed the soft ERCuNi wire without kinking.
MIG on Cuni is more sensitive to wind and draught than on carbon steel. Set up wind shields when working on deck.
When the WPS calls for tight heat input control — for example, on thin-wall condenser tubes or where distortion must be minimised — pulsed MIG and pulse TIG give a stable arc at lower average current. Pulse parameters are typically specified by the machine manufacturer and qualified on a test coupon before production welding.
If the project specification demands a process outside this list, qualify it through a separate PQR — do not assume it transfers from carbon-steel procedures.
Filler and gas choice is the most common place where site teams get the procedure wrong. Use the table below as the starting point for your WPS.
| Base material | Recommended filler | Standard | Shielding gas | Notes |
|---|---|---|---|---|
| 90/10 Cu-Ni (C70600) | ERCuNi | AWS A5.7 / EN ISO 18273-A CuNi 90/10 | Ar 99.99% | Default for seawater service. |
| 70/30 Cu-Ni (C71500) | ERCuNi (high-Ni type) or CuNi 70/30 rod | AWS A5.7 / EN ISO 18273-A CuNi 70/30 | Ar 99.99% | Used in higher-temperature, higher-corrosion service. |
| 90/10 to 70/30 joint | ERCuNi 70/30 | As above | Ar 99.99% | Always weld towards the higher-nickel side. |
| Cuni to Monel 400 (B165) tube | ERNiCu-7 | AWS A5.14 | Ar 99.99% | For transition joints in chemical service. |
A few rules that are easy to forget in the workshop:
When the pipe transitions to a different alloy — for example, where a Cuni line meets a B167 Ni-Cr-Fe alloy tube in a power-plant feedwater system — the filler and heat input must be qualified for the dissimilar joint, not just the parent alloys.
Heat input is the single most important number to record on every Cuni weld. EEMUA 144/234 do not give a single maximum value, but industry practice is to stay within 1.0-1.5 kJ/mm for TIG root passes and 1.5-2.5 kJ/mm for fill and cap.
Heat input is calculated as:
Heat input (kJ/mm) = (Voltage × Current × 60) / (Travel speed × 1000)
Worked example for a TIG root pass on a 3 mm wall 90/10 tube:
Always record actual current, voltage, travel speed, and interpass temperature on the weld log. If the welder deviates, the QA team has data to assess the joint instead of guessing.
A Cuni weld is not finished when the arc stops. The post-weld sequence below should be in the WPS and on the inspection and test plan (ITP).
Pressure-test the completed system at 1.5 times the design pressure (or as the project specification requires) for at least 30 minutes. Use clean freshwater; chloride-rich seawater in a hydrostatic test can mask leaks and damage the Cuni surface.
When the welded line is connected to flanged equipment, the bolted joints must be torqued to the WPS value using a calibrated wrench — and the gasket must be the type specified for Cuni service, typically compressed graphite or PTFE. See the pipe fittings and pipe flanges ranges for compatible components.
Three defects show up most often on Cuni welds. Each one is preventable with the right procedure.
Cause: contaminated surface, impure shielding gas, moisture in the filler. Procedure response: enforce cleaning, replace gas cylinders below 20 bar, store filler dry, and run a porosity test on the procedure qualification plate before production.
Cause: high heat input combined with sulphur or phosphorus over the EEMUA limit. Procedure response: cap heat input, verify chemistry on the MTR, and preheat thick sections to 100-150 °C when wall thickness exceeds 8 mm.
Cause: travel speed too high or arc too long. Procedure response: set realistic travel-speed limits, monitor arc length visually, and require a backing gas on every root pass.
Before the welder strikes the arc, the supervisor should be able to tick every box below. If any box is unchecked, do not start welding.
Following this checklist, combined with the procedures above, gives a EEMUA 144/234 weld that will pass NDT on the first attempt and stay leak-free for the design life of the system — whether it is carrying seawater across a ship’s engine room, feedwater through a petrochemical facility, or coolant through a heat-exchanger bundle built from B466 copper-nickel tube.
Related Products